
2021 Updated Verified Pass PRINCE2-Agile-Foundation Exam - Real Questions & Answers
Dumps Moneyack Guarantee - PRINCE2-Agile-Foundation Dumps Approved Dumps
PRINCE2 PRINCE2-Agile-Foundation Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
NEW QUESTION 21
Which role is responsible for facilitating the Agilometer assessment?
- A. Team manager
- B. Customer subject matter expert
- C. Project manager
- D. Project board
Answer: C
NEW QUESTION 22
Which is often used during a retrospective to capture lessons?
- A. A Kanban board
- B. A burn chart
- C. A Glad! Sad! Mad! board
- D. A Gantt chart
Answer: C
NEW QUESTION 23
What needs to happen when new detailed requirements are added to a timebox?
- A. The delivery milestones should be reviewed and re-planned
- B. More people should be added to the delivery team
- C. Formal change control should be applied
- D. Requirements of a similar level of effort should be removed
Answer: D
NEW QUESTION 24
Which statement explains the setting of the cost tolerance for a project in an agile context?
- A. Cost tolerance is flexed
- B. Cost tolerance can be fixed or flexed
- C. Cost tolerance can be fixed and flexed
- D. Cost tolerance is fixed
Answer: A
NEW QUESTION 25
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It is achieved by allowing enough time for testing
- B. It delivers the early realization of benefits
- C. It is achieved by using the same team members
- D. It gives confidence on the progress of the project
Answer: B
Explanation:
Reference:
%20level%20is%20met
NEW QUESTION 26
Which is typically used in agile when estimating detailed requirements during sprint planning?
- A. Visioning
- B. Trading
- C. Rationalism
- D. T-shirt sizing
Answer: C
NEW QUESTION 27
During which process should release planning be done for the FIRST time?
- A. Controlling a stage
- B. Initiating a project
- C. Managing product delivery
- D. Managing a stage boundary
Answer: D
NEW QUESTION 28
What information is NOT typically displayed on a burn chart?
- A. Actual amount of work done
- B. Amount of time elapsed
- C. Effort remaining
- D. Definition of 'ready'
Answer: D
NEW QUESTION 29
Which statement describes the Kanban approach?
- A. It was originally focused in creating new companies and is now used to speed up product delivery
- B. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
- C. It is an iterative timeboxed approach that helps teams generate value
- D. It is used to make system improvements using visualization and by controlling work in progress
Answer: D
NEW QUESTION 30
Which process can take place during a release review workshop?
- A. Managing a stage boundary
- B. Controlling a stage
- C. Managing product delivery
- D. Directing a project
Answer: C
NEW QUESTION 31
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
- A. Using visualization to display information
- B. Using meeting minutes to share decisions
- C. Using email to document discussions
- D. Using social media to reach more people
Answer: A
NEW QUESTION 32
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.
- A. 1 and 2
- B. 1 and 4
- C. 2 and 3
- D. 3 and 4
Answer: B
NEW QUESTION 33
Which is a typical characteristic of 'business as usual' work?
- A. It requires a specific dedicated project manager
- B. It is executed by program management
- C. It is delivered by an established team
- D. It is delivered by a temporary team
Answer: C
NEW QUESTION 34
Which is a key objective of running a workshop?
- A. To encourage collaboration and create the defined outputs from the event
- B. To make day-to-day decisions on behalf of the delivery team within a sprint
- C. To make daily progress visible to the delivery team and key stakeholders
- D. To communicate decisions to the wider stakeholder community
Answer: A
NEW QUESTION 35
What should be decided when configuring PRINCE2 effectively?
- A. Which areas are not enabled to work with agile
- B. What to remove and where to add guidance
- C. Where to put the emphasis and where to add guidance
- D. What to significantly change to create the right blend
Answer: D
NEW QUESTION 36
Which BEST describes the senior user role when tailoring the organization theme?
- A. An 'agile sponsor'
- B. A 'coach'
- C. An 'executive sponsor'
- D. A 'super product owner'
Answer: D
NEW QUESTION 37
Which statement about the 'keep teams stable' target is CORRECT?
- A. It prevents compromising the overall quality level of the product
- B. It applies primarily to the long term, such as a project or a program
- C. It is the primary reason why the tolerance for cost is set to zero
- D. It results in the early delivery of a minimum viable product
Answer: C
NEW QUESTION 38
Which is a reason for releasing a product into a staging area?
- A. It enables the faster delivery of changes
- B. It supports management by exception
- C. It supports regulatory compliance checking
- D. It enables a phased Waterfall approach
Answer: C
Explanation:
Reference:
%20and%20verification%20process
NEW QUESTION 39
How does agile address the risk associated with the project not being fully understood at the beginning?
- A. By allowing a lot of detail at the start
- B. By requiring details at the start
- C. By avoiding too much detail at the start
- D. By preventing the analysis of details at the start
Answer: D
NEW QUESTION 40
What term is used to describe boards that display what work needs to be completed for people working on a project?
- A. Information radiator
- B. Work in progress limit
- C. Highlight report
- D. Glad! Sad! Mad!
Answer: C
NEW QUESTION 41
......
Updated PDF (New 2021) Actual PRINCE2 PRINCE2-Agile-Foundation Exam Questions: https://www.prep4away.com/PRINCE2-certification/braindumps.PRINCE2-Agile-Foundation.ete.file.html
Verified PRINCE2-Agile-Foundation Exam Dumps PDF [2021] Access using Prep4away: https://drive.google.com/open?id=1VJv2q3rJqjsjI0NdvxhbhoBzAVTH7W58