NEW QUESTION 18
In the SAP Best Practices Time Recording - Project-Based Services (J12) scenario, which of the following settings can be enabled via SSCUI Maintain Data Entry Profiles? Note: There are 3 correct Answers to this question.

  • A. Switch on or off the approval process
  • B. Enable the field 'Work Location' to allow users to enter work location when recording the time in timesheet application
  • C. Switch on the field 'All Project Phases' to enable timesheet posting to be made regardless of project status
  • D. Switch on the field 'Extensibility Mode' to enable the extensibility of the timesheet application
  • E. Enable the field 'WBS Element' to allow users to specify the project task they are recording time against

Answer: A,B,D

 

NEW QUESTION 19
In the SAP Best Practices Internal Project Management - Project-Based Services (1A8) scenario, which account assignment categories are supported when maintaining settlement rules? Note: There are 3 correct Answers to this question.

  • A. WBS element
  • B. G/L account
  • C. Network
  • D. Cost center
  • E. Project

Answer: A,B,D

 

NEW QUESTION 20
Which components are required to integrate SAP S/4HANA Cloud with SAP Project Companion? Note:
There are 3 correct Answers to this question.

  • A. SAP Cloud Platform Identity Authentication
  • B. SAP CoPilot
  • C. SAP Concur
  • D. SAP Cloud Platform Mobile Services subscription
  • E. SAP Cloud Platform consumer account

Answer: A,D,E

 

NEW QUESTION 21
Which of the following are primary tasks of Project Managers? Note: There are 3 correct Answers to this question.

  • A. Create customer invoice
  • B. Maintain project billing
  • C. Create billing proposal
  • D. Plan work packages and efforts
  • E. Maintain project staffing

Answer: B,D,E

 

NEW QUESTION 22
When can you add relationships in the Organizational Structure? Note: There are 2 correct Answers to this question.

  • A. After one entity has been created
  • B. After content activation
  • C. During content activation
  • D. Before initial content activation

Answer: A,C

 

NEW QUESTION 23
What are customers able to scope in SAP S/4HANA Cloud with Central Business Configuration (CBC)?
Note: There are 2 correct Answers to this question.

  • A. Scope extensions
  • B. Countries where business processes will run
  • C. Non-standard scenarios
  • D. Pre-defined scenario bundles
  • E. Public sector processes

Answer: C,D

 

NEW QUESTION 24
What can you use the View Browser app to do?

  • A. Display released analytical queries
  • B. Display released analytical queries and authorized custom queries
  • C. Get a list of all available analytical CDS views and their artifacts
  • D. Launch analytic cloud stories

Answer: B

 

NEW QUESTION 25
In which implementation phase do you perform data load preparation?

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: A

 

NEW QUESTION 26
Under which circumstances would the Resourse Manager receive multiple resource requests for the same project or work package? Note: There are 2 correct Answers to this question.

  • A. A project usually consists of multiple work packages, which may require multiple roles.
  • B. A work package can contain more than one request for the same project role.
  • C. A resource request can represent multiple project roles that need to be staffed.
  • D. A resource request for a work package may require multiple resources.

Answer: B,D

 

NEW QUESTION 27
Which of the following functions are available when you create billing documents from the billing due list items? Note: There are 3 correct Answers to this question.

  • A. Create a collective billing document for multiple billing due list items
  • B. Create an individual billing document for each processed billing due list item
  • C. Log billing document information messages
  • D. View billing document details
  • E. Run parallel processing for billing document creation

Answer: A,B,D

 

NEW QUESTION 28
In case temporary adjustments have been entered, which of the following tasks can be performed to adjust the recognized revenue? Note: There are 2 correct Answers to this question.

  • A. Adjust PoC manually
  • B. Execute a periodic revenue recognition run
  • C. Recalculate planned values at work package level
  • D. Recalculate revenue recognition for the affected WBS elements

Answer: B,D

 

NEW QUESTION 29
Which replication scenarios are supported through the integration between SAP S/4HANA Cloud and SAP SuccessFactors Employee Central? Note: There are 3 correct Answers to this question.

  • A. Timesheet data
  • B. Cost center data
  • C. Employee data
  • D. Bank data
  • E. WBS element data

Answer: A,B,C

 

NEW QUESTION 30
What are the available methods through which you can fill staging tables in the SAP HANA database of the target system? Note: There are 3 correct Answers to this question.

  • A. XML templates
  • B. SAP Smart Data Access
  • C. SAP HANA Smart Data Integration (SDI)
  • D. Customer's ETL tools
  • E. SAP SQL Anywhere

Answer: A,C,D

 

NEW QUESTION 31
What is the purpose of the SAP Best Practices Intercompany Processes - Project-Based Services (16T) scenario?

  • A. Posting of invoices and simultaneous posting to the accounts payable of the ordering company
  • B. Creation of purchase orders and simultaneous creation of sales orders in the delivering company
  • C. Creation of the outbound delivery and simultaneous creation of the inbound delivery in the receiving company
  • D. Posting of the goods issue and simultaneous posting to stock in transit in the receiving company

Answer: A

 

NEW QUESTION 32
You are reviewing the Open Resource Requests KPI card in the Fiori app Resource Management for Projects. What are the possible urgency groupings? Note: There are 2 correct Answers to this question.

  • A. Upcoming
  • B. Very High
  • C. Overdue
  • D. Critical

Answer: B,C

 

NEW QUESTION 33
Which apps enable you to access the queries related to Maring Analysis & Utilization Analysis? Note:
There are 2 correct Answers to this question.

  • A. Custom CDS Views
  • B. Query Browser
  • C. Create Customer Projects
  • D. View Browser

Answer: A,D

 

NEW QUESTION 34
Which of the following are benefits of the SAP Best Practices Event-Based Revenue Recognition - Project-Based Services (1IL) scenario? Note: There are 3 correct Answers to this question.

  • A. Margin calculation
  • B. Reconciliation
  • C. Full transparency
  • D. Real-time reporting

Answer: B,C,D

 