[Q51-Q69] Accurate & Verified 2024 New PSK-I Answers As Experienced in the Actual Test!

Share

Accurate & Verified 2024 New PSK-I Answers As Experienced in the Actual Test!

PSK-I Certification Sample Questions certification Exam


Scrum PSK-I, also known as Professional Scrum with Kanban level I, is a certification exam that focuses on the integration of Scrum and Kanban methodologies. PSK-I exam is designed to assess an individual's understanding of how Scrum and Kanban can work together to improve team performance and enhance project management. Scrum is a framework for agile project management that emphasizes collaboration, flexibility, and continuous improvement. Kanban, on the other hand, is a lean methodology that focuses on visualizing work, limiting work in progress, and optimizing flow.


Scrum PSK-I Certification Exam is an online assessment consisting of 80 multiple-choice questions that need to be completed within 60 minutes. PSK-I exam is designed to evaluate the understanding of the Scrum framework, including its values, principles, roles, events, and artifacts, and how it can be enhanced with Kanban. PSK-I exam is challenging, and candidates should be well-prepared to ensure their success.

 

NEW QUESTION # 51
True or False: Scrum Events, Scrum Team Accountabilities, and Scrum Artifacts are changed when using Scrum with Kanban. For example, the Scrum Team might choose to omit the Sprint Retrospective when using Kanban with Scrum.

  • A. False
  • B. True

Answer: A


NEW QUESTION # 52
True or False: Kanban in a Scrum context does not require any additional events to those outlined in the Scrum Guide.

  • A. FALSE
  • B. TRUE

Answer: B


NEW QUESTION # 53
Which of the indicators would be more helpful at the Daily Scrum? (choose the best answer)

  • A. Leading indicators.
  • B. Lagging indicators.

Answer: A


NEW QUESTION # 54
True or False: The way the Developers approach the Sprint Goal at the Daily Scrum changes if they are using Kanban. Choose only ONE best answer.

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 55
True or False: The Sprint length can be thought of as the team's batch size with Scrum Teams using Kanban.

  • A. TRUE
  • B. FALSE
  • C. Choose only ONE best answer.

Answer: B


NEW QUESTION # 56
Which of the following is true if the Developers allocate a percentage of their capacity for unplanned work during the Sprint Planning? (choose the best answer)

  • A. The Sprint Goal becomes more important. It can help the Developers their focus as new Product Backlog items are pulled into their Sprint Backlog.
  • B. Reserving capacity for unplanned work should not be allowed as it introduces risks of failing to deliver on their commitment.
  • C. The value of the Sprint Goal decreases as less work is dedicated to the objective.

Answer: A


NEW QUESTION # 57
True or False: The level of collaboration within a Scrum Team will likely reduce when applying Work in Progress (WIP) Limits.

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 58
What is the flow metric used to forecast the number of items that will be finished per unit of time. (choose the best answer)

  • A. Lead time.
  • B. Cycle time.
  • C. Work in Progress (WIP).
  • D. Throughput.

Answer: D


NEW QUESTION # 59
Only a Product Owner and Developers are the needed when applying Kanban in Scrum.

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 60
What would be the most appropriate reason for a Scrum Team to adjust their Work in Progress (WIP) Limits? (choose the best answer)

  • A. When the Developers receive unplanned urgent work during the Sprint.
  • B. When they want to improve their cycle time, workflow, and focus.
  • C. When the work in progress is lower than the capacity of the Developers.
  • D. When the velocity of the Scrum Team velocity becomes too low.

Answer: B


NEW QUESTION # 61
True or False: Releases are limited to the end of the Sprint cycle when Scrum Teams use Kanban.

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 62
True or False: Work in Progress (WIP) Limits should primarily apply to tasks related to an individual Product Backlog item in the Sprint Backlog.

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 63
Workflow can be thought of as the Scrum Team's policy for which of the following? (choose the best answer)

  • A. What completed work looks like.
  • B. How to increase the Team's WIP limit.
  • C. How to get work done.
  • D. Defining when development is complete and validation begins.

Answer: C


NEW QUESTION # 64
When using Kanban in Scrum, a team needs to use which of the following four metrics of flow? (choose the best four answers)

  • A. Lead Time
  • B. Work in Progress (WIP)
  • C. Throughput
  • D. Work Item Age
  • E. Cycle Time
  • F. Cumulative Flow Diagram (CFD)

Answer: B,C,D,E


NEW QUESTION # 65
Reducing batch sizes might have the following impact: (choose all that apply)

  • A. Highlight a need to improve processes/infrastructure to reduce the pain of frequent costly overhead.
  • B. Higher motivation due to seeing your work get done and deliver value earlier.
  • C. Lower efficiency due to overhead/transaction costs in case the batch size is too small.
  • D. Improving efficiency due to faster feedback loops.

Answer: A,B,C,D


NEW QUESTION # 66
True or False: 'On-demand' work item place holders are used in place of Sprint Goals for Scrum Teams using Kanban. Choose only ONE best answer.

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 67
A Kanban board is comprised of which of the following policies? (choose the best two answers)

  • A. Work in Progress (WIP) Limits.
  • B. Class of service policy.
  • C. Your workflow visualization.
  • D. Each Product Backlog Item type has a separate swim lane.

Answer: A,C


NEW QUESTION # 68
The team needs to work on a high priority urgent unplanned item, but they are at their WIP limit.
True or False: They should change the WIP limit at their Daily Scrum to enable them to pull in that item.

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 69
......