NEW QUESTION 35
You are performing an SAP S/4HANA conversion. When does the silent data migration (SDM) take place?
- A. During the SUM technical downtime
- B. Before the start of the SUM technical downtime
- C. After SUM has ended
- D. During the Execution roadmap step
Answer: A
NEW QUESTION 36
What is the minimum SAP_BASIS release of an SAP ECC system that can be converted to an SAP S/4HANA Server?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: A
NEW QUESTION 37
You are performing an S/4HANA conversion of the development system. Which credentials do you use in which system to perform the adjustment of dictionary objects (SPDD)?
Please choose the correct answer.
Response:
- A. Credentials of user DDIC in the development client of the development system
- B. Credentials of a named user in the development client of the development system
- C. Credentials of user DDIC in client 000 of the shadow system
- D. Credentials of a named user in client 000 of the shadow system
Answer: D
NEW QUESTION 38
You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime.
The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center you can see 40 Process Buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
Please choose the correct answer.
Response:
- A. The number of CPU cores does not allow more than 40 R31oad processes to be run in parallel.
- B. SUM is still running in uptime; the number of 40 defined R31oad processes is considered.
- C. These are 40 pairs of R3load processes, so there are 80 R3load processes running.
- D. There is a maximum of 40 parallel R31oad processes within this specific downtime phase.
Answer: C
NEW QUESTION 39
Which additional configuration options are offered by SUM when selecting "Switch expert mode on" in main configuration option "Standard"?
There are 2 correct answers to this question.
Response:
- A. Keep archiving on during the whole procedure.
- B. Use the Near Zero Downtime Maintenance Technology (NZDM).
- C. Reuse a profile for the shadow instance from a previous run.
- D. Choose the instance number of the shadow instance.
Answer: C,D
NEW QUESTION 40
Regarding an SAP Upgrade, What does the major SAP Note for the version of SUM you are using usually contain?
- A. AA
- B. The link to different patch levels to SUM
- C. The corrections to the SUM Guide
- D. An overview about possible upgrade paths
Answer: B,C,D
NEW QUESTION 41
You downloaded content from the SAP note 1000009 ("ASU Toolbox 2008"). Which transaction needs to be executed to use that content in the ASU Toolbox?
Please choose the correct answer.
Response:
- A. /ASU/SHOW_NOTE (Show SAP Note via Web-Browser)
- B. /ASU/SSM (ASU Simple Schedule Manager)
- C. /ASU/START (Start ASU Toolbox)
- D. /ASU/UPGRADE (Start ASU Toolbox in Upgrade Mode)
Answer: C
NEW QUESTION 42
During a SUM run you want to check if the phase SHADOW_IMPORT_INC is still running properly. Where can you find information about this?
There are 2 correct answers to this question.
Response:
- A. Check for running R31oad processes on the host of the primary application server
- B. Check for running R3trans processes on the host of the primary application server
- C. Check for the latest log files in the SUM directory, subdirectory ABAP, subdirectory tmp
- D. Check for running batch jobs in the shadow system via Job Overview (SM37)
Answer: B,C
NEW QUESTION 43
You are running an SAP ECC system with SAP_BASIS 740, non-Unicode on SAP MaxDB. Which of the following are possible paths to perform an SAP S/4HANA conversion? Note: There are 3 correct answers to this question.
- A. Unicode conversion Upgrade to SAP ECC with SAP_BASIS 750 including database migrationSAP S/4HANA conversion without database migration
- B. Unicode conversion SAP S/4HANA conversion including database migration
- C. Unicode conversion Database migration SAP S/4HANA conversion without database migration
- D. Unicode conversion SAP S/4HANA conversion without database migration Database migration
- E. SAP S/4HANA conversion including database migration and Unicode conversion
Answer: A,B,C
NEW QUESTION 44
You are planning to upgrade your SAP ECC 6.07 system running on a single codepage (SCP) to SAP ECC 6.08. What is the recommended option to perform this upgrade?
Please choose the correct answer.
Response:
- A. Combine the upgrade and the Unicode conversion using the Twin Upgrade &Unicode Conversion (TU &UC) procedure.
- B. Perform the Unicode conversion before the upgrade to SAP ECC 6.08.
- C. Combine the upgrade and the Unicode conversion using the Combined Upgrade &Unicode Conversion (CU &UC) procedure.
- D. Perform the upgrade to SAP ECC 6.08 before the Unicode conversion.
Answer: B
NEW QUESTION 45
You are performing an inplace SAP S/4HANA conversion including DMO. What is the latest point in time when you can reset the procedure without losing data?
- A. The start of the business downtime
- B. The end of the business downtime
- C. The end of the database migration
- D. The start of the Execution roadmap step
Answer: B
NEW QUESTION 46
What do you need to consider when performing the SI checks for an SAP S/4HANA conversion? There are 2 correct answers to this question.
- A. You need to build up a SI check framework by applying SAP notes.
- B. The SI checks are executed in the development system and the results are transported into the subsequent systems.
- C. Depending on the SAP S/4HANA version, there are different SI check frameworks.
- D. You need an SAP system based on AS ABAP 7.50 or above for the SI check framework.
Answer: A,C
NEW QUESTION 47
What do you do to prepare the database migration option of a SUM procedure?
There are 3 correct answers
Response:
- A. Move the stack.xml update file into the download folder
- B. Move the R3trans update archive into the download folder
- C. Extract the SAP HANA database installation archive
- D. Extract the SAP HANA client installation archive
- E. Move the SAPM update archive into the download folder
Answer: A,D,E
NEW QUESTION 48
In which scenarios do you need to use SUM 2.0 instead of SUM 1.0?
There are 2 correct answers to this question.
Response:
- A. SAP S/4HANA conversion to SAP S/4HANA 1709
- B. Updating to SAP ECC 6.07 using DMO
- C. Upgrading to SAP ECC 6.08 without using DMO
- D. Using DMO when applying Support Packages to SAP ECC 6.07
Answer: A,C
NEW QUESTION 49
You are running an SAP ECC system. For which of the following activities does SUM allow you to use the Near Zero Downtime Maintenance (NZDM) capabilities?
There are 3 correct answers to this question.
Response:
- A. Perform an SAP S/4HANA conversion including DMO.
- B. Apply an Enhancement Package.
- C. Upgrade the SAP system.
- D. Use DMO for SUM.
- E. Apply SAP Support Packages.
Answer: B,C,E
NEW QUESTION 50
In which case can you use near-Zero Downtime Maintenance (nZDM)? Note: There are 2 correct answers to this question.
- A. When upgrading an SAP ECC system with DMO
- B. When upgrading an SAP S/4HANA Server system
- C. When performing an SAP S/4HANA conversion without u DMO
- D. When performing an SAP S/4HANA conversion with DMO
Answer: A,B
NEW QUESTION 51
You want to perform custom code check via ABAP test cockpit in preparation of your SAP S/4HANA conversion? What kind of SAP System can you use to generate the custom code migration worklist?
- A. AA
- B. A Standalone SAP system with ABAP 7.51 or above
- C. An SAP S4HANA 1709 sandbox system
Answer: B,C
NEW QUESTION 52
What are the benefits of using the Benchmarking option of the DMO for SUM?
There are 2 correct answers to this question.
Response:
- A. You can find the optimal number of parallel R31oad processes by monitoring host performance.
- B. You can obtain migration duration files that can be used to optimize the next runs from a previous benchmark run.
- C. You can verify that the content of the download directory matches the stack.XML file.
- D. You can record the modification adjustment during migration and use the transports in the next runs.
Answer: A,D
NEW QUESTION 53
What is the main purpose of performing benchmark runs for an SAP S/4HANA conversion?
- A. To optimize the conversion
- B. To optimize the main import
- C. To optimize the activation
- D. To optimize the migration
Answer: D
NEW QUESTION 54
You are performing an SAP S/4HANA conversion with DMO as an inplace migration. How does SUM transfer the data by default from the source database to the target database during the migration?
- A. Using work processes and network socket connection
- B. Using R3load and network socket connection
- C. Using R3load and memory pipes
- D. Using R3load and file transfer
Answer: C
NEW QUESTION 55
......